Planning is essential to project management and organising work. Contributors are free to make plans however they please or make none at all. However, the root contribution circle uses a specific model in order to document progress and assess the future.

This system helps the root contribution circle in several ways:

  • Principally helps us to explore problems more deeply before working on a solution to a particular problem. As otherwise it is easy to converge on a solution without considering the bigger picture.
  • Keeps work and planning transparent and easy to share with the draupnir longhouse assembly. So it is easy to explain to stakeholders what is being worked on and why.
  • Makes it easier to check that work is implemented correctly and to a high quality.
  • Helps new contributors to onboard as the tasks show them which parts of the project to change.
  • Preserves a record of decisions and history of problem exploration that is well documented.

Planning essentials

In order to understand the planning system, you need to understand some basic rules of planning and the trade-off between certainty and agility.

The more concrete a plan is, the less agile it is. And as we know requirements and the world is never static, and plans need to adapt over time. The trick to managing this is to make sure that plans become more detailed the closer they are to being implemented. And that certainty about the cost of plans can only become more detailed as more work is done to develop them. Keeping plans abstract and untied to implementation keeps them agile.

The same is also true for exploring a problem space, you learn much more about problems while working on solutions to them than you do by hypothesizing solutions to them. And this is another reason why plans need to be adaptive.

This is also why it is important for work to be incremental. It allows problems to be explored in smaller units, while keeping other aspects of a plan abstract, and thus adaptive to change from exploration.

The final mechanic to balance is that by concreting plans later, we are more likely to know more about the problem, and less likely to have to rework the solution. If the plans that we turn concrete are smaller, the less risky the plan is and we give ourself more opportunity to learn.

This implies that there is also a planning decay to existing plans. The older the plan, the more outdated the knowledge. And plans that are more detailed and concrete decay faster than more abstract plans.

Overview

Draupnir's planning system is layered:

Problem -> Bet -> Solution -> Increment -> Task.

Bet, Increment, and Task serve planning purposes, while Problem and Solution serve design purposes.

  • Problems give us high level context of large systemic issues or feature requests.

  • Solutions give us an exploration and design space for solving a problem.

  • Bets give us high level abstract plans to explore a solution, wagered against the value we gain from succeeding, and the maximum value we can commit to exploration before sunk-cost.

  • Increments give us concrete plans defined in terms of deliverables to learn about a solution to a problem and provide value. That can be delivered within a longhouse cycle. Increments are usually only materialized directly before the longhouse cycle they will be used in, specifically to prevent planning decay.

  • Tasks provide very focussed and details plans for units of work.

So the layers really exist in two tiers:

  • Planning tier: Bet -> Increment -> Task.
  • Design tier: Problem -> Solution.

Both interact and feed each other.

Problems

Problems are more of a strategic mechanism than a planning mechanism. They provide the context that allow plans to be made. And provide an adapting rolling discussion about a problem based on experience gained from exploration.

After triage issues are consolidated into a "bigger picture" discussion that captures and describes the problem. This is done at as higher level as possible without implementation detail. It is extremely important to refrain from the temptation to describe the problem in a way that precludes it to a specific solution. Keeping the problem abstract gives us the opportunity to consider our options and the trade-offs with each of them. This is strategically significant as without this step, the consideration likely will not happen.

Problems should have the following properties:

  • A list of actors involved.
  • The current workflow for the problem, how does the system already work
  • The problems with this workflow and what commands / prompts / protections are involved in the interaction.
  • A concise high level description of what the actors are attempting to achieve with the current workflow in the absence of implementation detail, commands, prompts, or protections.
  • A specific high level analysis of the problem in the absence of implementation detail.
  • No requirements or language that attempts to form requirements is used at all. This is not the place for requirements engineering. As this risks sneaking solutions into the problem statement

Problems should also record the following:

  • A list of issues that are considered
  • The triage score of those issues
  • A list of solutions that have been explored
  • Possibly an analysis of why a solution failed if exploration brought us back to the problem space.

Bets

note

Bet's are derived from James's shore's blog post the accountability problem.

Bets are provisional hypotheses about high level objectives. They are not designs or solutions, they encapsulate the value of pursuing an objective and the maximum material cost we are willing to pay to achieve the objective. These are important to make because they allow us to be accountable to the use of resources with respect to value. Which is not only important for strategic management.

Bets are also the long-term planning unit that we expose to third parties to discuss material support for the project. And we have to be able to do this at a high level, further away from the planning horizon so that we can maintain agility1.

Present value and wager

Bets are crucially defined in terms of their present value (which is what we gain if the bet succeeds) and the wager (what we are willing to commit to the bet, and lose, before it is recognised as a failure).

  • Opportunity cost: What is lost or gained by pursuing an objective relative to other objectives, and within the environment. For example, if there is an ongoing attack vector being used in the wild that there is a designed solution for, there is lost opportunity by not working on it.

  • Value, what is valuable to the draupnir project is contributor time, user pain (see triaging), and opportunity cost.

  • Present value: The user pain erased, the opportunistic value, the learning value in terms of problem exploration, the compound value in terms of advancing us to other goals.

  • Wager, the amount of contributor time that we're willing to wager against the bet before it's time to move on or create a new bet. This is not, and cannot be how much the bet costs or an estimate of cost because we don't know enough about the problem at this high level. It's a commitment of the maximum value we are prepared to lose in order to pursue the objective. Because we might get no value at all from pursuing the bet. This stops us from getting stuck in sunk cost.

Commitment

This is an explanation of what the objective is, which problems we are solving or making progress on, and any other context.

Other risks that can fail the bet

These are other factors that can fail the bet other than exhausting the wager. E.g. if an MSC doesn't pass, or if another third party solution arises.

Deliverable meaningful results

These are used to know how we know if bet has produced its intended value. They are not a specification, success or acceptance criteria, because we need agility. The outcomes should not prescribe implementation detail. They are very abstract and refer to solving associated problems, and abstract deliverables.

These are here so that we can demonstrate that the bet has succeeded to stakeholders through public artefacts, such as releases of features, documentation, or publication of research results.

Solution hypotheses

Once a problem has been described, a solution can be designed. These are speculative designs about how to solve a problem, capturing and recording insight at any time while context is fresh on a contributor's mind. The purpose is to preserve ideas and thought.

Solutions should have the following properties:

  • An approach for how the problem is going ot be solved.
  • An overview of any risks with the approach or any trade-offs.

If a line of work through increments makes a discovery that compromises the solution, then a new solution should be created after the problem is updated.

Solutions should be iterated from feedback experienced from working on tasks and increments.

Increment

note

Increments are derived from James Shore and Shane Warden's adaptive planning book.

An increment represents a small end-to-end unit of delivery that advances a bet's commitment. The outcomes are always observable and are completable within one longhouse cycle. The bet commitment is advanced by either creating value or by providing insight into solutions. Increments are usually always materialized immediately before the cycle they are used in to prevent planning-decay.

The observable value is usually:

  • A new feature being released in Draupnir.
  • Documentation being published.
  • New infrastructure being deployed and accessible to stakeholders.
  • New understanding of a problem or solution that is written up in the planning system.

Discovery tasks should be included under increments that have uncertainty or need refinement.

Increments include details about:

  • The bet they are associated with and how they advance the commitment.
  • The success criteria with reference to actors.
  • A list of tasks that break down the solution into workable units.
  • An overview of any planning risks with the approach or any trade-offs.

Deliverable Tasks

Once a solution hypothesis has been designed. The solution needs to be broken down into instructions for work that can be delivered. These tasks are the only planning issue that can be reliably estimated in development cycles with.

Tasks are also used to document any work that has been undertaken.

Tasks should explain very specifically what protections, commands, library code is going to be edited and how.

Tasks can be thought of as "document what you intend to change and work on before you change it". It helps to build a picture of the size of the task without actually committing to or doing much work. They also help contributors less familiar with the project pick up work easily.

Solutions may have one task which is to simply explore the problem space and write up the other tasks. A workload cycle would then simply only include this one task.

Tasks typically include:

  • A high level description of the task.
  • A description of what pieces of software are going to be changed.
  • The acceptance criteria for the task.
  • The details of any work undertaken on the task.

For a concrete problem, Tasks should typically be created for:

  • Implementation how-to for a specific part of a deliverable.
  • Regression test for a piece of functionality.
  • End-user documentation is to be created for a deliverable.
  • Implementation how to for a library change that may be required.
  • Discovery placeholders when library changes have other dependants.
  • Development documentation for new patterns or abstractions.

For a planned problem, Tasks should be created for:

  • Research and planning tasks for deriving or exploring a solution.
  • Refinement placeholders when solutions remain abstract.

Review

Work that is completed should first be reviewed against the solution, and then reviewed against the original problem

Success vs acceptance criteria

Success criteria are related to solutions, they're related to the problem and are always grounded with actors.

Acceptance criteria aren't grounded with actors and are specific to making sure important aspects of the task are complete.

Common actors

Contributor

Someone who contributes to the draupnir project.

Room moderator

A moderator for a room on Matrix.

Homeserver administrator

A moderator managing users resident to a Matrix homeserver, and rooms that the homeserver is joined to.

System administrator

This is someone who is deploying and managing draupnir at a software systems level, rather than someone who necessarily uses it.

Why we do not use story pointing

Story pointing may work in some environments. We used to use it for this project but we have identified some weaknesses:

  • We do not have reliable historical information on completion of other tasks, it's also very difficult to do this if you need to change methodologies.
  • The bigger a story is, the more inaccurate the estimate is going to be, because there is going to be less detail and less consideration with reference to the implementation.

We also became prone to Goodhart's law: "When a measure becomes a target, it ceases to be a good measure". If you note that you work on 20 story points in a week, you'll start scoring things to fit that. It is very difficult to avoid this bias and everyone involved has an interest to score lower or higher.

Using Tasks as the fundamental unit of work means that they are always grounded in the implementation. And there is no estimation of task size required, they're all the same size.